One of the 36 bridges at ECE2 project is Bridge over Terengganu River, up to April 2008, the progress is 93 %
Efendi as planning coordinator of MTD Construction Sdn Bhd. We are inviting for sharing of information for Projects : Planning,Scheduling,Project Management,Progress Reporting and Shofware application
Friday, May 23, 2008
Thursday, May 22, 2008
Information of East Coast Expressway Phase 2 (ECE2) Project

Lebuhraya Pantai Timur Fasa 2 Project is part of the East Coast Expressway(ECE2) connecting Kuala Lumpur to the East Coast State Pahang, Terengganu and Kelantan.
The highway is design as a 4 lane dual carriageway with a design speed of 120 km/h. Phase 2 start at Jabur and end at Kp. Gemuruh, 20 km to city of Kuala Terengganu.
The government divided the highway into 12 packages. Package 10 was awarded to MTD under LLM. The highway length for Package 10 is 79 kilometer. The main alignment form Bukit Besi to Bukit Payong is 63.3 km in length with design speed of 120 km/h and Bukit Payong to Spur Road is 15.7 km with design speed of 90 km/h.
The project duration is 30 months commencing from 18 September 2006 to 17 March 2009.
The highway is design as a 4 lane dual carriageway with a design speed of 120 km/h. Phase 2 start at Jabur and end at Kp. Gemuruh, 20 km to city of Kuala Terengganu.
The government divided the highway into 12 packages. Package 10 was awarded to MTD under LLM. The highway length for Package 10 is 79 kilometer. The main alignment form Bukit Besi to Bukit Payong is 63.3 km in length with design speed of 120 km/h and Bukit Payong to Spur Road is 15.7 km with design speed of 90 km/h.
The project duration is 30 months commencing from 18 September 2006 to 17 March 2009.